Abstract: The construction sequence of a reinforced concrete castinpace pile is to open a hole at the proposed pile location, place the rebar cage into the hole and then place the concrete. This technique receives a wide application due to its relatively matured construction technique, reliable quality, low cost, high bearing capacity as well as applicable to a wide range of soil strata. This paper presents a case study of the installation of castinpace piles for a pipeline project in Yellow River Floodplains. The construction results of the submerged reinforced castinplace concrete piles in these soil strata are also introduced.
Key words: Cast-in-Place Piles, Submerged Drilling, Floodplains, Construction Control
HE Xiaojun. Construction Techniques of Submerged Drilling for Cast-in-Place Piles at Yellow River Floodplains[J]. , 2013, 27(4): 55-57.
0 / / Recommend
Add to citation manager EndNote|Reference Manager|ProCite|BibTeX|RefWorks
URL: https://tgjc.whrsm.ac.cn/EN/
https://tgjc.whrsm.ac.cn/EN/Y2013/V27/I4/55