Soil Engineering and Foundation ›› 2020, Vol. 34 ›› Issue (2): 145-151.

Previous Articles     Next Articles

The Design and Practice of Foundation Pit Engineering Combining the Top-down Method for the Annex Building and Ordinary Excavation Method for Main Building

DI Guoen1,2   

  1. (1.East China Architecture Design & Research Institute Co., Ltd., Shanghai Underground Space & Engineering Design Institute, Shanghai 200011;
    2.Shanghai Engineering Research Center of Safety Control for Facilities Adjacent to Deep Excavations,Shanghai 200011)
  • Received:2020-04-07 Revised:2020-04-16 Online:2020-05-20 Published:2020-05-20
  • Supported by:
    (Scientific research plan of Shanghai Science and Technology Commission)

Abstract: Based on the second phase project of Nanjing Deji square, this paper introduces the design and practice of deep foundation pit engineering combining the topdown method for the annex building and ordinary excavation method for main building, and summarizes the key technologies and countermeasures of the combination of the topdown method for the annex building and ordinary excavation method for main building. The results monitoring show that the combination of the topdown method and ordinary excavation method greatly accelerates the construction progress of the annex building, achieves the established construction goal, effectively protects the surrounding environment, saves social resources, and achieves good social benefits, which can provide reference for similar projects.

Key words: underground space development, deep foundation pit, the topdown method, one column with one pile, changement of shear wall structures