›› 2011, Vol. 25 ›› Issue (6): 11-.
Previous Articles Next Articles
ZHANG Qing1, MOU Chun mei1, LI Wang xing2
Received:
Online:
Published:
Abstract: The procedures and technical details of pre\|stressed ground anchor installations are presented throughout a case history in a red clay soil cut slope construction located in a section of the Shuige, Guizhou Prov. of the Xiamen\|Chengdu Expressway Project. The pre\|stressed ground anchors along with the reinforced concrete anchor frames were tested and monitored in the project. A cost saving was achieved compared with other slope stability methods.
Key words: red clay soils, high cut slope, pre\, stressed ground anchors
ZHANG Qing1, MOU Chun mei1, LI Wang xing2. Application of Pre\|stressed Ground Anchors in High Cut Slopes in Red Clay Soils[J]. , 2011, 25(6): 11-.