Discussions on the BoxCulvert Foundations for the Xiaochang Natural Gas Station Project

TAN Zhanting   

  1. (Hubei Province Natural Gas Development Co., Ltd., Wuhan, 430074)
  • Received:2013-12-24 Online:2014-12-25 Published:2015-01-12

Abstract: This paper discusses the technical issues encountered during the construction of box culvert for the Xiaochang Natural Gas Station. These adverse situations include, soft soil stratum, new deposited loose soils, irrigation canal, etc. The topography and geotechnical conditions of the project site are also introduced in the paper. The box culvert was successfully constructed.

Key words: Box-culvert Foundations, Soil Improvements, Construction Techniques