土工基础 ›› 2025, Vol. 39 ›› Issue (2): 208-212.

• 工程实录 • 上一篇    下一篇

TBM穿越断层破碎带卡机风险预测与控制研究

蹇宜霖,刘夏临,彭文波   

  1. (中交第二公路勘察设计研究院有限公司,武汉 430056)
  • 收稿日期:2024-12-27 修回日期:2025-01-03 出版日期:2025-04-30 发布日期:2025-06-03
  • 作者简介:蹇宜霖(1991-),男,硕士,助理工程师,研究方向为隧道设计。

Risk Prediction and Control of TBM Machine Crossing A Fault Zone

JIAN Yilin, LIU Xialin, PENG Wenbo   

  1. (CCCC Second Highway Consultants Co. Ltd., Wuhan 430056)
  • Received:2024-12-27 Revised:2025-01-03 Online:2025-04-30 Published:2025-06-03

摘要: TBM卡机风险预测及脱困处理就成为高效掘进的关键控制点,天山胜利隧道服务隧道采用敞开式TBM掘进,隧道穿越16条断层破碎带,卡机风险高。针对天山胜利隧道可能存在卡机风险的断层破碎带,建立了基于断层破碎带变形预测与TBM扩挖量相结合的卡机预测方法,并将其应用于天山胜利隧道卡机预测,分析每条断层的卡机风险程度。研究了断层破碎带注浆加固体效果,为TBM隧道提供超前加固技术。在TBM需脱困时,采用化学灌浆、管棚加固、迂回导洞、导洞开挖卸荷多种措施并举,保证安全脱困。通过TBM施工前风险预测,对隧道中的断层破碎带采取针对性措施,施工中采取超前加固对策,TBM卡机后采取合理的脱困措施,使隧道TBM施工安全、高效。


关键词: TBM卡机, 风险预测, 超前加固, TBM脱困

Abstract: The risk prediction and emergency mitigations of the TBM excavation jamming have become the key control points for an efficient tunneling project. The service tunnel of the Tianshan Shengli Tunnel uses an open-type TBM for the excavation, and the tunnel passes through 16 faults, which poses a high risk of jamming the TBM. For the fault zones with potential jamming risks in the Tianshan Shengli Tunnel, a jamming prediction method based on the deformation prediction of fault zones and the TBM enlargement volume was established, and it was applied to the jamming prediction of the Tianshan Shengli Tunnel to analyze the degree of jamming risk in each fault. The effect of the grouting consolidation of fault zones was studied, it provides advanced reinforcement technology for the TBM tunnel. When the TBM needs to be released, chemical grouting, bracing with grouting pipes, detour tunnel, and tunnel excavation and unloading measures can take together to ensure a safe construction. By conducting the risk prediction before the TBM construction, take specific measures to the fractured zone of fault in tunnel, provide reinforcement measures during the construction. After the TBM is jammed, take reasonable mitigation measures, so that the TBM construction in the tunnel is safe and efficient.

Key words: TBM Jamming, Risk Prediction, Advance Reinforcement, TBM Jamming Release

中图分类号: