›› 2018, Vol. 32 ›› Issue (6): 594-598.

• 工程实录 • 上一篇    下一篇

平潭综合管廊深基坑内支撑支护优化设计与分析

胡红亮   

  1. (中铁一局集团有限公司,西安 710054)
  • 收稿日期:2018-07-11 修回日期:2018-07-18 出版日期:2018-12-20 发布日期:2018-12-21
  • 作者简介:胡红亮(1982-),男,工程师,研究方向为综合管廊施工技术。
  • 基金资助:

    中铁一局集团有限公司技术研发项目(2017A-043)

Optimization Design and Analysis of Deep Excavation Internal Strut Supported for an Integrated Utility Culvert in Pintan

HU Hongliang   

  1. (China Railway First Group Co., Ltd., Shaanxi, 710054)
  • Received:2018-07-11 Revised:2018-07-18 Online:2018-12-20 Published:2018-12-21

摘要: 为合理设计地下综合管廊深基坑内支撑支护结构,以平潭综合实验区地下管廊深基坑工程为研究背景,将原设计中最上面1道混凝土撑优化成钢管撑,利用PLAXIS 3D岩土有限元分析软件建立优化前后三维数值模型,模拟地下综合管廊深基坑开挖支护过程,计算2种支护结构的受力情况。计算结果表明:相对原设计,优化后的围护墙弯矩最大值637.6 kN·m,变化幅度0.82%~3.09%;围护墙侧移变化形态基本一致,降幅为0.33%~1.36%。总体上优化前后对基坑的受力变形影响不显著。通过对管廊基坑的监测数据分析,表明基坑总体上安全稳定,优化后的内支撑设计安全可靠。该优化方案的实施还加快了施工进度,取得了良好经济效益。

关键词: 地下综合管廊, 深基坑, 内支撑, 优化设计, 现场监测

Abstract: This paper presents a case history of Value Engineering design and analysis of the internal strut supported deep excavation for an integrated utility culvert in Pintan. The original excavation support option was the drilled and castinplace reinforced concrete piles with one castinplace reinforced concrete waler supporting system plus two layers of steel pipe strut supporting system. The first castinplace reinforced concrete waler system in the original design had the disadvantages of low construction efficiency and high cost, and therefore, the optimized design converted into steel pipe strut support. The excavation sequence was simulated through a threedimensional finite element analysis using PLAXIS software. The stressstrain in the original and new supporting system were compared. The results indicate that, the maximum bending moment in the optimized system was 637.6 kNm/m or varying from 0.82% to 3.09%. The lateral deflections at the supporting system were similar with only 0.33% to 1.36% reduction. It was therefore concluded that the stressstrain changes in both system were not significant. The new supporting system was applied in the construction. From the construction monitoring results, the safety of the excavation could be ensured and the internal supporting system was reliable and was cost effective. The construction schedule was also accelerated.

Key words: Integrated Utility Culvert, Deep Excavation, Internal Strut Support, Optimized Design, Construction Monitoring