AutoCAD civil3D软件在矿山治理工程量计算中的应用

樊亚莉1,庞家伟2,肖凤荣2   

  1. (1.青岛地矿岩土工程有限公司,山东青岛 266000;2.青岛中油岩土工程有限公司,山东青岛 266071)
  • 收稿日期:2020-04-22 修回日期:2020-04-28 出版日期:2021-06-25 发布日期:2021-06-25
  • 作者简介:樊亚莉(1988-),女,工程师,研究方向为水文地质。

Application of AutoCAD Civil3D in Quantity Estimation of an Abandoned Mine Rehabilitation Project

FAN Yali1, PANG Jiawei2, XIAO Fengrong2   

  1. (1.Qingdao Geotechnical Engineering Co. Ltd., Qingdao 266000;
    2.Qingdao China Petroleum Geotechnical Engineering Co. Ltd., Qingdao 266071)
  • Received:2020-04-22 Revised:2020-04-28 Online:2021-06-25 Published:2021-06-25

摘要: 削坡开阶及土石开挖和回填是废弃矿山生态环境治理工程中常见的工程措施。削坡和回填土石方量计算的准确性是决定施工进度的重要环节,传统计算软件包括南方Cass、mapgis等,均具有计算过程冗杂、时间长、改一处动全身等缺点,软件之间来回切换、转换也会增加不必要的工作。应用Civil3D软件进行计算,土石方量计算可根据设计曲面的改动而变化,其计算结果精确,调整操作少,实时显示调整结果,可以提供更加直接、全面的视觉感官效果,能够最大限度优化设计,节省工程投资。

关键词: Civil 3D, 矿山治理, 工程量, 3D模型

Abstract: In recent years, the rehabilitation of mine ecological environment projects has developed rapidly. Slope cutting, benching, soil or rock excavation and backfilling are common engineering measures that are frequently in the ecological environment control projects of abandoned mines. The accuracy of earthwork quantity estimation of slope cutting and backfilling is an important task to determine the construction schedule. The traditional earth work quantity estimation software, including South CASS and MAPGIS, has the disadvantages of complicated calculation process, long computation time and coupling parameters etc. Switching and conversion between software modules will also increase unnecessary computational work. This paper presents a case history of using Civil 3D software for the estimation of earth work quantity. The earthwork volume can be changed according to the change of design surface. The quantity estimation results are accurate, with less adjustment operation and have a real-time display of adjusted result. It can provide more direct and comprehensive visual display effect, optimize the design to the maximum extent and save project investment.

Key words: Civil 3D, Mine Rehabilitation Project, Earth Work Quantity, 3D Model