存在淤泥层的管线沟槽支护实例

彭 莹1,罗红兵2   

  1. (1.成都兴蜀勘察基础工程公司,成都 610070;2.中机三勘岩土工程有限公司,武汉 430030)
  • 收稿日期:2013-04-22 出版日期:2014-04-21 发布日期:2014-04-25
  • 作者简介:彭莹(1989-),助理工程师,研究方向为基坑支护、地基基础、滑坡治理。

Pipeline Excavation Instance In Silt Layer

PENG Ying1,LUO Hongbing2   

  1. (1.Chengdu Xingshu Geotechnical Investigation & Foundation Engineering Co., Ltd, Chengdu 610072;
    2.China  Machinery TIDI Geotechnical Engineering Co.,Ltd., Hubei Wuhan, 430030)
  • Received:2013-04-22 Online:2014-04-21 Published:2014-04-25

摘要: 市政管线开挖往往存在开挖深度大,回填较快,工期较短,支护路线长的特点,结合管线开挖实例,介绍场地存在淤泥层时的管线支护方案设计,实际施工监测结果证实该设计方案可行。

关键词: 管线支护, 淤泥, 排桩, 支撑

Abstract: Municipal pipe line installation projects are characterized to have a relative large excavation depth, quick backfill, short construction duration and long excavation support horizontal length. A case history of pipeline excavation project is presented in this paper to demonstrate the design, construction and construction monitoring aspects of the project site with a soft mucky soil layer.

Key words: Pipeline Excavation Supports, Mucky Soils, Piles, Supporting System