土工基础 ›› 2026, Vol. 40 ›› Issue (2): 296-299.

• 专题论述 • 上一篇    下一篇

宽大异形基坑分区施工对邻近轨道交通结构安全的风险研究

查红星,尉胜伟,潘新发,焦斌斌,李金彪   

  1. (苏州轨道交通集团有限公司,江苏苏州 215008)
  • 收稿日期:2024-11-19 修回日期:2024-12-02 出版日期:2026-04-30 发布日期:2026-04-23
  • 作者简介:查红星(1969-),男,高级工程师,研究方向为轨道交通安全。

Study on the Risk of Partitioned Construction of a Large and Irregular Deep Excavation to the Safety of Adjacent Rail Transit Structures

ZHA Hongxing, YU Shengwei, PAN Xinfa, JIAO Binbin, LI Jinbiao    

  • Received:2024-11-19 Revised:2024-12-02 Online:2026-04-30 Published:2026-04-23

摘要: 依托邻近苏州轨道交通3号线何山站的苏地2023-WG-63号地块基坑工程,建立三维仿真计算模型,分析了宽大异形基坑分区施工对既有轨道交通结构的安全影响。研究结果表明:宽大异形基坑根据不同深度采用分区施工,既有轨道交通结构的变形主要发生在基坑开挖阶段,且B区基坑开挖为主要影响阶段;基坑开挖对车站附属的影响大于对车站主体的影响,且以竖向变形为主;基坑开挖时按照“先深后浅、先远后近”的施工方式可有效减少车站结构变形和位移,保证既有车站和区间的运营安全。


关键词: 宽大异形基坑, 轨道交通, 车站结构, 区间结构, 数值仿真

Abstract: This paper focuses on the deep excavation project of Block Sudi 2023-WG-63, located adjacent to Heshan Station on Suzhou Metro Line No. 3. Based on the unique characteristics of deep excavation and its relative position to the metro structure, a three-dimensional simulation model was established using three-dimensional modeling software to analyze the safety impact of partitioned construction of a large and irregular-shaped excavation on the existing metro structure. The research results indicate that the deformation of the existing metro structure primarily occurs during the excavation phase, with the excavation of Area B being the most significant phase of impact. The excavation has a greater effect on the ancillary facilities of the station than on the main station structure, and the deformation is mainly vertical. Adopting a construction sequence of “deep before shallow, far before near” during excavation can effectively reduce deformation and displacement of the station structure, guaranteeing the safe functioning of the current stations and sections.

Key words: Large and Irregular Deep Excavations, Rail Transit, Station Structure, Section Structure, Numerical Simulation

中图分类号: