深基坑二次加固支护及监测分析

蔡文华1,钟家焕2   

  1. (1.中建八局第一建设有限责任公司,济南 250000;2.广东省国际工程咨询有限公司,广州 510000)
  • 收稿日期:2023-10-31 修回日期:2023-11-21 出版日期:2026-02-28 发布日期:2026-04-22
  • 作者简介:蔡文华(1992-),男,硕士研究生,工程师,国家一级建造师(中级工程师),研究方向为岩土工程。

Deep Excavation Secondary Reinforcement Support Design and Monitoring

CAI Wenhua1, ZHONG Jiahuan2   

  1. (1.First Construction Co. Ltd., China Construction Eighth Bureau, Jinan 250000;
    2.Guangdong International Engineering Consulting Co. Ltd., Guangzhou 510000)
  • Received:2023-10-31 Revised:2023-11-21 Online:2026-02-28 Published:2026-04-22

摘要: 以广州市海珠区某深基坑项目为背景,在原支护结构的基础上结合目前基坑周边环境、开挖深度及岩土层地质情况进行基坑支护二次加固设计方案选型分析,确定了加固设计方案为:高压旋喷桩+灌注桩(已施工但监测合格)+预应力锚索(二次施工)。设计相应的基坑工程监测方案,并对支护结构和周边环境等实测数据进行分析。结果表明:①桩顶水平位移,竖向累计水平位移随着开挖的进行数值随之增大,但在设计和规范允许的范围内;②基坑边地表沉降距坑边的距离是先增大后减小最后趋于稳定;③桩锚支护二次加固方案是比较合理的,研究结果可为停工基坑项目的后续设计与施工提供参考。

关键词: 深基坑, 桩锚支护, 二次加固, 施工监测, 位移

Abstract: This paper presents a case history of a deep excavation secondary excavation supporting system design and monitoring in Haizhu District, Guangzhou City. The original excavation support structure design, adjacent environment, excavation depth, and subsurface conditions are introduced, and the secondary supporting system design options are also presented. The reinforcement design option adopted is as follows: high-pressure jet grout + cast-in-place reinforced concrete piles (already installed and accepted by the construction inspection) + prestressed ground anchors (secondary improvement installations). The correspondent excavation monitoring system are also designed and the excavation process as well as the adjacent structures are monitored. The results show that: 1) the horizontal displacement of the soldier pile top and the vertical cumulative horizontal displacement increase with the excavation depth, but within the  allowable range defined by the design and specification; 2) the surface settlement of the edge excavation is firstly increasing and then decreasing and finally tends to a stable state; 3) the soldier pile and ground anchor support secondary reinforcement program is more reasonable, and the results of the study can provide a reference for the subsequent design and construction similar projects.

Key words: Deep Excavation, Soldier Pile and Ground Anchor Support, Secondary Improvement, Construction Monitoring, Displacement