土工基础 ›› 2022, Vol. 36 ›› Issue (6): 1006-1012.

• 测试技术 • 上一篇    

高边坡稳定分析及开挖防护监测设计

李兆宇   

  1. (中国水利水电第三工程局有限公司,西安 710024)
  • 收稿日期:2022-10-13 修回日期:2022-10-24 出版日期:2022-12-31 发布日期:2022-12-28
  • 作者简介:李兆宇(1978-),男,高级工程师,研究方向为道路桥梁隧道工程。

Stability Analysis, Cut and Construction Monitoring Design of a High Slope

LI Zhaoyu   

  1. (Sinohydro Bureau 3rd Co. Ltd., Xian 710016)
  • Received:2022-10-13 Revised:2022-10-24 Online:2022-12-31 Published:2022-12-28

摘要: 为保证高铁安全运营,以京沈客运专线承德南站大里程端线路右侧DK187+000.00~DK187+315.00段边坡为例,分析了边坡稳定性,进而对比分析了边坡稳定防护方案,并对边坡变形进行了监测。结果表明,支挡结构边坡在天然工况下,产生小规模局部溜滑,位于距坡顶陡壁10 m附近,厚度为2~3 m,滑塌体主要堆积于坡体中部,坡度33°时趋于稳定;在降雨+地震工况下,边坡上部塌滑在距坡顶20 m附近,最厚处达3~5 m,滑塌体主要堆积于坡脚,28°时趋于稳定。通过比选,选择清除边坡松散坡积体,挖除全部全~强风化岩采取支护加强方案。边坡坡率控制在1∶1~1∶1.5,边坡每8 m设置平台,平台宽度为2 m。下部山体开挖对上部的卸荷及变形产生一定的影响。

关键词: 高边坡, 边坡稳定, 支挡结构, 监测

Abstract: To ensure the safe operation of the high-speed railway, the slope stability between Station DK187+000.00 and DK187+315.00 on the right side of the Chengde South Railway Station of Beijing-Shenyang passenger special line is analyzed as a case history. The slope stability mitigation measures were compared, analyzed. The cut slope deformation during the construction was also monitored. The results show that, under natural conditions, the retaining structure for the slope produced small local slippage, which was mainly concentrated at about 10m from the top of the steep wall, with a thickness of 2 ~ 3m, and mainly accumulated in the middle of the slope body. The deformation tended to be stable when the slope angle reached 33°. Under the condition of the rainfall and the earthquake, the upper part of the slope collapses about 20m away from the top of the slope, and the thickest part reaches 3-5m. The slope deformation mainly accumulated at the foot of the slope, and they tended to be stable when the slope angle reached 28°. Throughout the comparison and selection, the loose slope deposits of the slope were removed, and all the strongly to completely weathered bedrock were removed and supported. The angle of the side slope was controlled in the range of 1V:1H to 1V:1.5H. The platform was set every 8m of the slope height, and the width of the platform was determined to be 2m. The excavation of the lower mountain has some influence on the unloading and deformation of the upper part.

Key words: igh Slope, Slope Stability, Retaining Structure, Construction Monitoring