土工基础 ›› 2021, Vol. 35 ›› Issue (4): 434-437.

• 工程实录 • 上一篇    下一篇

某高填方地基处理设计

董鹏程1,汤 伟2,郭胜娟3   

  1. (1.昆明市五华区国有资产投资经营管理有限公司,昆明 650228;2.云南省设计院集团有限公司,昆明 650228;
    3.云南水务投资股份有限公司,昆明 650106)
  • 收稿日期:2020-05-29 修回日期:2020-06-17 出版日期:2021-08-31 发布日期:2021-08-19
  • 通讯作者: 汤 伟(1985-),男,高级工程师,注册岩土工程师,研究方向为岩土工程。
  • 作者简介:董鹏程(1975-),男,高级工程师,研究方向为施工技术管理。

Ground Improvement Design of a Large Fills

DONG Pengcheng1, TANG Wei2, GUO Shengjuan3   

  1. (1.Kunming Wuhua District State Asset Investment Operation and Management Co. Ltd., Kunming 650228;
    2.Yunnan Design Institute Group Co. Ltd., Kunming 650228;
    3.Yunnan Water Resource Investment Co. Ltd., Kunming 650106)
  • Received:2020-05-29 Revised:2020-06-17 Online:2021-08-31 Published:2021-08-19

摘要: 云南某工程原始地形高低起伏较大,冲沟发育,沟深超过20 m,场地分台平整后回填深度仍达到10~35 m,由于工期紧张,场地回填平场完成后立即要施工主体工程和场区道路挡土墙,因此,采用何种方法处理地基及如何控制工后沉降成为本工程的最大技术难点。经技术方案及经济造价对比后采取了分层强夯及分层碾压+铺设加筋格栅的方式进行处理,工程竣工后,经过四年的沉降监测,结果表明本工程场地工后沉降量较小,沉降量满足设计和工程使用要求,取得了较好的社会和经济效益。

关键词: 高填方, 强夯, 分层碾压, 沉降

Abstract: This project is located in Yunnan Province. The original site terrain has significant variation in elevations with well-developed erosion gullies with depth up to 20 meters deep. During the site preparation, the site fill height would vary from 10 to 35 meters. Due to the tight construction schedule, the site would be filled immediately after the site grading was completed. Since the project main structure construction and the roadway retaining wall were located in the fill area, so that that soil improvement for the post construction settlement mitigation were critical to the success of this project. After the feasibility and cost comparison of various soil improvement methodologies, dynamic compact method and the layer compaction plus geogrid reinforcement methods were finally selected. After the completion of the project, the settlement monitoring was lasted for four years and the results showed that the site initial settlement after construction was relatively small and meets the design and engineering requirements.

Key words: High Fills, Dynamic Compaction, Layered Compaction, Settlement

中图分类号: